Beijing Fortune Financial Center Reroofing project

       

 

The building is an international Grade A office tower, located in the core area of Beijing CBD, with a building height of 265 meters. It holds LEED Gold and WALL Health and Safety Certifications and is home to numerous world-leading enterprises and financial institutions.

The leakage has affected the normal use of the top floor of the building and the underground garage, so it is necessary to carry out a special leakage treatment for the building. The construction difficulty of the project and the on-site management and control requirements are extremely strict.

After selection, investigation and thorough demonstration by the property owner and the property management company, Beijing Guzhuo Construction Engineering Co., Ltd. was finally chosen to customize a "customized systematic waterproofing solution that combines coating and the waterproofing membrane together, balances rigidity and flexibility, integrates prevention and drainage, and conducts comprehensive treatment" for the client.

This customized service integrates international top-notch waterproof materials and technical resources and provides professional empowerment. Sika PVC waterproofing membranes are used for large-area construction, and Triflex waterproof coatings are used for key detail treatment.

System Advantages:

1)Sika PVC membranes feature excellent aging resistance and ultraviolet resistance, and have obtained a BBA certification for an ultra-long service life of up to 35 years.

2)The German-imported Triflex PMMA coating waterproofing system is applicable to complex nodes (roofs, glass domes, balconies, walkways, pools, etc.); it has an ETA-certified durability of over 25 years; it is resistant to ponding water, root penetration, crack bridging, fading, ultraviolet rays, and does not require a protective layer; it can seamlessly lap with SBS, PVC, TPO waterproofing membranes, concrete, glass, metal, wood and other substrates; and it fully cures in 45 minutes, shortening the construction period.

3)The entire construction process is flameless and cold-applied.

Through the unremitting efforts of the professional team, the project was successfully completed and concluded with remarkable results, winning high recognition from the client.